Temporary stop bank work holds up in most recent rain event

stop bank work

Rapid work by Hawke’s Bay Regional Council (HBRC) staff and contractors last week (20-25 Feb.) to shore up stop bank breaches on four rivers held up during the most-recent rain event.

In the first stage of the Rapid Rebuild programme Council staff prioritised temporary solutions for 11 stop banks breaches in the Ngaruroro, Tutaekuri, Tukituki and Waipawa rivers.
Incident Controller and HBRC Group Manager-Asset Management, Chris Dolley says he is proud of the work that was completed in just six days.


“We developed a system to identify the highest-risk locations and send resources to use bunding (gravel mounding) and other methods to provide some protection if there was a rain event. This turned out to be prudent given the rain that came through the province on Friday and Saturday.”


“Our team deserves a huge pat on the back for their quick solution to these issues,” Mr Dolley says.


HBRC crews are now pivoting to get on with more permanent repairs – work that will take months. Using a pod system, there are now 13 self-contained crews at work making steady progress toward restoration of the stop bank system.

“We have a lot of work ahead of us, but I think the people of Hawke’s Bay should be confident that we are getting on with it as quickly as we can. This most-recent success in preventing any leakage or outflow from riverbeds is an example of how we are starting to restore our system,” says Mr Dolley.

 

27 February 2023

Back to News Archive

Disclaimers and Copyright
While every endeavour has been taken by the Hawke's Bay Regional Council to ensure that the information on this website is accurate and up to date, Hawke's Bay Regional Council shall not be liable for any loss suffered through the use, directly or indirectly, of information on this website. Information contained has been assembled in good faith. Some of the information available in this site is from the New Zealand Public domain and supplied by relevant government agencies. Hawke's Bay Regional Council cannot accept any liability for its accuracy or content. Portions of the information and material on this site, including data, pages, documents, online graphics and images are protected by copyright, unless specifically notified to the contrary. Externally sourced information or material is copyright to the respective provider.

© Hawke's Bay Regional Council - www.hbrc.govt.nz / +64 6 835 9200 / info@hbrc.govt.nz